It is common for employers and contractors to fall into dispute over suspended projects and their recommencement, particularly in regards to time and costs, changes in design and scope of works. With many projects that were stalled during the Covid pandemic, and the period of lower oil prices, now being restarted, Curtis provides an overview of the key issues to consider together with the main causes of disputes and how to successfully navigate restarting suspended projects.
Pre-Suspension Losses
Contractors should consider what losses they may have incurred prior to a project being suspended. It is very common that, prior to receiving an instruction to suspend works, the employer will have slowed the contractor down in their works which will have caused a loss in productivity. A contractor should consider whether a claim for prolongation or disruption exists prior to suspension.
To establish disruption, a contractor would be required to undertake a review of its productivity in carrying out the works over the schedule in order to determine when lower productivity occurred and what work activities were impacted. It is likely expert analysis will be required to determine the loss of productivity arising out of the disruption events, and the resulting financial loss. As always, good records are essential.
Suspension
- Costs incurred protecting the works against any deterioration, loss or damage.
- Downtime/standing time of plant/equipment and labour.
- Depreciation of equipment.
- Prolongation costs – staff, insurance, bonds, extended warranties, accommodation, storage facilities.
- Making good unavoidable deterioration of the works.
- Loss of revenue.
- Interest.
- Other general damages suffered.
- Minutes of meetings.
- Site inspection records.
- Daily, weekly and monthly reports.
- Schedules/programs.
- Design documents.
- Equipment logs.
- Photographs of progress and key milestones.
- Is there an agreed and documented procedure for restarting?
- Is the design still correct and/or viable?
- Is the existing project execution plan still workable?
- What project documentation/records are still in place?
- Is it possible to jointly agree a condition survey with the employer?
- Can variations be agreed prior to recommencement?
- How are the project restart works priced?
- Is timing, sequence and quantity agreed?
- What is the basis of pricing the restart works?
- What is the impact of suspension/restart on the project’s material costs?
- Has there been any impact by inflation, escalation, commodity prices, availability of material?
- Have suppliers changed during the suspension period and, if so, does this impact time or cost?
- Is it necessary to revisit BOQs and rates/prices?
- Will there be a need to replace already installed material? There have been significant increases in prices during 2020-2022 of concrete, steel, cabling, timber. This should be factored in and agreed before restarting works.
- Have there been any regulatory or procedural changes during the period of suspension that have increased costs during remobilization?
- Any changes in regulation also may impact pricing if specified materials have changed or are no longer available due to supply chain restrictions, sanctions, or availability of materials produced overseas.
- Are subcontractors still available?
- Has the introduction of VAT had any impact on costs?