Tuesday, March 24, 2020

Issuance of Health Insurance Rules


In October 2019, the Capital Market Authority (the “CMA”) issued Ministerial Decision 78/2019 Issuing the Health Insurance Rules (the “Rules”) in respect of the Unified Health Insurance Policy (the “Policy”), the details of which were previously issued under Ministerial Decision 34/2019 and discussed in our July 2019 article, Oman Rolls Out Unified Health Insurance Policy – or ‘Dhamani.’  The Rules set out the obligations of the various stakeholders in the health insurance relationship, i.e., insurers, third-party administrators, health services providers, employees and employers.
Insurance coverage
The Rules provide that the Policy will determine the extent of the health insurance coverage to be provided under the Policy, provided that such coverage should not be below the basic health services the insured should enjoy.
Insured persons are entitled to cancel their health insurance policy at any time by providing 30 working days’ prior written notice, in which case the insurer is required to refund the insured the amounts in respect of the cancelled term in accordance with the terms of the insurance policy.  Such refund should be provided within 30 working days of the date of cancellation of the insurance policy.
The amount of the insurance premium will have to be agreed on between the parties, as long as such premium does not exceed the market pries for health insurance in Oman.
The health insurance coverage will expire under the following circumstances:
          Expiration of the term of the insurance policy.
          Exhausting the maximum limit of the benefits under the policy.
          Death of insured.
          Departure of the insured expatriate out of Oman.
          Transfer of service of insured from one entity to another.
Any claims arising from a health insurance policy shall not be heard until one year has lapsed from the date of expiration of the relevant policy.  Statutes of limitations shall be considered paused by claim measures or procedures stipulated in the Rules.
Issuance of licence
The Rules provide that without prejudice to the provisions of Ministerial Decision E/31/2007 regarding licensing requirements for insurance companies, a company will also need to submit an application in the form stipulated in the Rules.  The CMA will examine the licence application within 60 days of submission.  In the event that the application does not provide all the required documents, the applicant is required to provide the required document within 30 days of being notified to do so.  Failure to provide the documents within the stipulated time period will result in the application being cancelled.  Once an application has been cancelled, another application cannot be submitted for a period of 90 days from such cancellation.  If the application is granted, the Executive President of the CMA will issue a decision granting the licence within 60 days of receipt of all the required documents within the prescribed time period.  If no decision is issued within the 60-day period, the application will be deemed to have been rejected.
A licence will be valid for a period of two years and renewable for similar periods.  The application for renewal will need to be submitted by the insurer at least 30 days prior to the expiration of the licence.
Provision of health insurance
All relevant parties are required to implement the Health Insurance Electronic Platform, as discussed in the Policy and in accordance with other decisions and notifications of the CMA.
Health insurance activities and operations may not be undertaken unless the relevant licence has been obtained from the CMA.  Healthcare providers licensed to provide health insurance services are barred from providing health insurance services unless they have satisfied the CMA’s enrollment requirements and paid the stipulated fees.
Except as permitted in accordance with the terms and conditions issued by the Executive President of the CMA, no insurer may own or operate a health care provider or third-party administrators, and no healthcare provider may own shares in companies licensed to undertake health insurance activities, insurance brokers or agents for health insurance companies, or third-party administrators.
Health insurance providers are required to retain a minimum of forty per cent. (40%) of the net health insurance premiums within Oman.
The Rules also set forth the obligations of the insurers, healthcare providers, and the insured vis-à-vis each other.
Health insurance dispute settlement committee
The Rules provide for a committee to be formed by a decision of the Executive President of the CMA to settle disputes arising from practicing health insurance activities.  The committee will be entitled to consider disputes arising between or among insurance providers, healthcare providers, the insured, third-party administrators and insurance brokers and agents; decide on claims that have been rejected, returned, or deducted by the insurance company; and any other matters which the Executive President deems necessary to bring before the committee.
The committee shall issue its decisions within 30 days from the date of the matter being put before it.  Concerned or interested parties will have the right to appeal against the decision of the committee to the Executive President within 60 days from the date of notification, or the date when the appellant became categorically or undoubtedly aware of the decision.  The appeal must be decided within 30 days from the date of its submission.  The expiry of the said period shall be considered as a rejection of the appeal.
Sanctions
Notwithstanding the sanctions listed under the Insurance Companies Law, the CMA shall be entitled to impose the below sanctions in the event of violation of the Rules:
          Warning.
          Administrative fine of OMR 1000-5000.
          Suspending the licence for a maximum of six months.
          Revocation of licence.
          Cancellation of healthcare service provider enrollment.

Read More...



Tuesday, March 17, 2020

The Commercial Companies Law One Year Later


The Commercial Companies Law promulgated by Sultani Decree 18/2019 (“CCL) was published in February 2019 and came into force 60 days after publication.  Please refer to our previous articles on this topic:
The CCL provides that the Minister of Commerce and the Chairman of the CMA will issue executive regulations within a year of the CCL’s implementation in addition to any decisions required to enforce the provisions of the CCL.  Currently, the draft executive regulations appear to be at an advanced stage and due for timely publication. 
Companies must comply with the requirements of the CCL within one year of its implementation – which means the deadline of 18 April 2020 is approaching fast.
For the first time, annual general meetings of joint stock companies, which must take place before 31 March each year, will be held under the new regime.  Many joint stock companies will take the opportunity to organise an extraordinary general meeting (“EGM“) on the same day and at the same venue to reduce the administrative burden of convening two separate general meetings.
The EGM will approve the amendments to the articles of association (“AoA”) required to be made to comply with the CCL.  This may also be an opportunity for companies registered many years ago to undertake a full review of their constitutional documents and make further amendments to align them with best practice and corporate governance.
Please note that the CMA has issued model articles that listed joint stock companies are expected to adopt, subject to the inclusion of additional clauses.
Please find below a summary of the most relevant changes introduced by the CCL in respect of the organisation of general meetings:
  1. The new deadlines mandated by the CCL apply.  The invitation to attend a general meeting must be published 15 days prior to the date of the meeting and must include both the date of the first and the second meeting (to be held within seven days from the date of the first meeting).  If the quorum is not met at the first meeting, the second meeting shall be held as provided in the invitation.
  2. General meetings must be attended by the directors (but their absence will not affect the validity of the meeting).
  3. Members of the board may not attend general meetings on behalf of the shareholders.
  4. The company must constitute an auditing committee from among the members of the board and  appoint  a  legal  advisor  and  an  internal auditor.
  5. Minutes of the general meetings must be signed by the secretary, the chairman, the auditor and the legal advisor and lodged with the competent authority within seven days calculated from the date following the date of the meeting.  The deadline under the previous law was 15 days.
Of course, the sections of the AoA regulating general meetings will have to be revised to reflect the provisions above.  Further changes may or will relate to:
  1. The number of directors of the company:   as the CCL provides for an odd number of directors, companies which currently have an even number of directors will have to decide whether they wish to add or remove one seat on the board of directors (subject to compliance with the minimum and maximum number of directors allowed for each type of company).
  2. The inclusion of more stringent provisions in respect of related party transactions and conflicts of interest.
Where changes are required, failing to comply with the provisions of the CCL within the deadline may result in the company, its authorised managers and/or directors being exposed to sanctions.

Read More...



Tuesday, March 10, 2020

Coronavirus and the Potential Impact on Construction Contracts in Oman


There is widespread economic impact as a result of the numerous factories that have suspended production in China due to the coronavirus, and with companies instructing many employees to work from home.  Construction activities are likely to be impacted worldwide as major suppliers are unable to meet delivery dates.  It is therefore timely to consider what contractors can do if faced with this type of delay.
The FIDIC Red Book
In the 1999 version of the FIDIC Red Book, a potential claim for an extension of time under Sub-Clause 8.4(d) should be considered for:
“Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions.”
This Sub-Clause is not often removed or amended in the Particular Conditions, and therefore provides entitlement for an extension of time, assuming of course that 28 days’ notice since becoming aware of the event or circumstance is provided, as per Sub-Clause 20.1.  In this context the “event or circumstance” would most likely be any notification from a supplier.
If problems become more serious, one may need to consider Force Majeure defined in Sub-Clause 19.1 as:
“an exceptional event or circumstance:
(a) which is beyond a Party’s control,
(b) which such Party could not reasonably have provided against before entering into the Contract,
(c) which, having arisen, such Party could not reasonably have avoided or overcome, and
(d) which is not substantially attributable to the other Party.”
Whilst the coronavirus event is not an “exceptional event or circumstance” of the kind listed following this definition, FIDIC makes clear that the list is not limited to those events.
Therefore, if the General Conditions are unamended at Sub-Clause 19.1, the Contractor could issue a notice under 19.2 within 14 days of becoming aware of the event or circumstance, which in turn could provide entitlement under Sub-Clause 19.4 to claim an extension of time.  However, it is interesting to note that to claim for some types of events listed in 19.1 (related to war, rebellion, riot, etc.), the event must occur in the country where the project is located, whilst for others (such as natural catastrophes) it does not.
Force Majeure can be limited in 19.1 strictly to the events or circumstances listed, by deleting “may include, but is not limited to” and then letting the list read as only the circumstances listed.  One could then turn to Employer’s Risks in Sub-Clause 17.3 and in particular argue that the coronavirus event is “any operation of the forces of nature which is Unforeseeable or against which an experienced contractor could not reasonably have been expected to have taken adequate precautions.”  Assuming that the Particular Conditions have not been amended to delete this provision as well (another common amendment), there would at least be entitlement to claim for an extension of time under Sub-Clause 17.4 (and 8.4(b)).  The advantage of claiming under 19.1, however, is the right to terminate the contract if the effect is prolonged as per 19.6, but care must be taken since this can work both ways:  either party may give such notice, thereby providing the employer grounds to terminate under the contract.
Under the 1987 FIDIC Red Book, there is entitlement to claim an extension of time under Sub-Clause 44.1(e) if considering the coronavirus as “special circumstances which may occur, other than through the default of or breach of contract by the Contractor or for which he is responsible.”  Notice should also be provided in this instance under 53.1.
The 1987 version of the FIDIC Red Book does not include Force Majeure although some of the Employer’s Risks listed at Sub-Clause 20.4 are considered as “Special Risks” at Sub-Clause 65.2.  The problem here is that the only Employer’s Risk that could apply to the coronavirus at 20.4(h) (“any operation of the forces of nature against which an experienced contractor could not have been expected to take precautions”) is not one of the Employer’s Risks taken to be a “Special Risk” at 65.5 where there is considerable scope to claim increased costs.  There is therefore no path to termination of contract but at Sub-Clause 66.1 there is still a possibility that a party may be released from further performance if “any circumstance outside the control of both parties arises after the issue of Letter of Acceptance which renders it impossible or unlawful for either or both parties to fulfill their contractual obligations.”
If therefore 20.4(h) has not been struck out in the Particular Conditions, there is a path for the contractor to recover any loss or damage arising from the coronavirus under 20.3 as a result of 20.4(h) by giving 28 days’ notice under 53.1.
The Oman Standard Conditions
There is no explicit provision for “force majeure” as such in the Sultanate of Oman Standard Conditions for Building and Civil Engineering Works Fourth Edition September 1999 (the “Standard Conditions”).  However, Clause 66 [Frustration] provides that:
“If … circumstances outside the control of both parties … arises … so that either party is prevented from fulfilling his obligations, or under the Law of the Sultanate of Oman, the parties are released from further performance, then the sum payable by the Employer to the Contractor in respect of the work executed shall be [the] same as that which would have been payable under the provisions of Clause 65 hereof.”
Clause 65 [Special Risks] of the Standard Conditions governs “Special Risks” and specifies in subsection 65(8) what payments the employer must make to the contractor in the event a contract is terminated as a consequence of the occurrence of a Special Risk, as defined in subsection 66(5).
Essentially, the contractor is entitled to:  payment for work executed prior to the date of termination; amounts payable for preliminary items; the cost of materials or goods ordered by the contractor for the works; expenditure incurred in expectation of completing the works; and any additional sums as provided earlier in Clause 66.
Omani law
Force Majeure is covered by Article 172 of the Oman Civil Code as promulgated by Sultani Decree 29/2013 (the “Civil Code”), which states:
“In contracts binding on both parties, if force majeure supervenes which makes the performance of the contract impossible, the corresponding obligation shall cease, and the contract shall be automatically terminated.”
The Civil Code does not define what constitutes force majeure, and the Omani courts have been reluctant to allow termination of a contract based on non-economic factors.  However, the courts have recognised that natural disasters may constitute circumstances that result in the frustration in the performance of a contract.
Whilst this article focuses on construction contracts, the issues discussed will likely apply to a broad range of commercial contracts.  We would be happy to assist any clients who have contracts that are impacted by delay.  As with managing all contractual delays, the key is to obtain advice and develop a strategy at the earliest possible opportunity. 

Read More...



Tuesday, February 18, 2020

Update on Exposure to U.S., U.K., E.U., and U.N. Sanctions

Given recent events in the region and abroad, it is timely to increase internal awareness of international economic sanctions, and give thought as to how they may impact your company’s current or future dealings. The issue is particularly important given that the newly passed Foreign Capital Investment Law (Royal Decree 50/2019) will likely lead to increased foreign investment into the Sultanate, and recently imposed sanctions have an impact on how companies can transact and trade with sanctioned nations and individuals.

We remind readers of our in-depth article on sanctions contained in our 1 September 2018 Client Alert, in which we discussed the U.S. having issued an Executive Order that re-imposed certain sanctions with respect to Iran as part of the United States’ withdrawal from the Joint Comprehensive Plan of Action.[1]

Since publication of that article, the relationships between Russia, Iran, Syria, and North Korea and the U.S., the U.K., and the E.U. have become ever more complex, and the levels of sanctions overall have increased (including with respect to the transfer of materials in specific sectors such as construction within sanctioned countries).

U.S. legislation enacted recently (such as the 2020 National Defense Authorization Act (“NDAA”)) authorises the imposition of sanctions on companies that provide goods, services, or other support for certain sanctioned countries. Of note and by way of example of growing sanctions, incorporated into the NDAA is the Caesar Syria Civilian Protection Act of 2019 (“Caesar Act”), which authorises sanctions on senior Syrian government officials, military leaders and others.

Of specific importance under the Caesar Act is the provision that those subject to sanctions include any individual or entity that “knowingly sells or provides significant goods, services, technology, information, or other support that significantly facilitates the maintenance or expansion of the Government of Syria’s domestic production of natural gas, petroleum, or petroleum products.”

This month, similar actions have been taken by President Trump by way of Executive Order against Iran, authorising the imposition of additional sanctions against any individual owning, operating, trading with, or assisting sectors of the Iranian economy including construction, manufacturing, textiles, and mining.

Types of sanctions


As a reminder, we outline below the structure of U.S. sanctions generally.

The U.S. Department of the Treasury’s Office of Foreign Assets Control (“OFAC”) is the primary body that enforces U.S. economic sanctions, which are imposed by Congress and the President through a combination of legislation and executive actions.

OFAC sanctions programs fall into two broad categories: “primary” sanctions and “secondary” sanctions. Primary sanctions apply to any “U.S. person,” which is defined to include any U.S. citizen or permanent resident alien, regardless of location; any person who is in the United States, regardless of nationality; and any entity organised under the laws of the United States or of any jurisdiction within the United States (and including that entity’s foreign branches). By contrast, secondary sanctions render every person and entity, anywhere in the world, subject to U.S. sanctions for engaging in certain activities or transactions with (or for the benefit of) specified individuals or entities, or with (or through) specified countries or regions.

Why are sanctions important to your business?


If a contract party is sanctioned, U.S. persons would be barred from providing funds, goods, or services to contract parties and their majority-owned companies and subsidiaries, and receiving funds, goods, or services from those parties. Non-U.S. persons would be effectively foreclosed from using U.S. dollars to transact business with the sanctioned party which could have potential implications for the financing of a project. In addition, non-U.S. persons could themselves risk becoming subject to sanctions based on their dealings with the primary sanctioned party.

E.U. and U.K. companies would likely follow suit due to the risk of themselves being sanctioned.

With respect to the U.K./E.U., if a contract party or its executives are added to the E.U.’s asset freeze list in the future, E.U. nationals would be prohibited from working on the potential project, and the affected Omani company would be unable to conduct any business within the E.U.

We note that following its departure from the E.U., the U.K. is likely to adopt existing E.U. sanctions, but may also implement its own additional sanctions in the future. This is another area that should be watched carefully.

Future sanctions


The risk of future sanctions being applied to a contract party or venture partner should be carefully considered before entering into a contract.

Usually the risk of future sanctions can be mitigated substantially by way of thorough due diligence, contractual representations and warranties, covenants requiring the divestiture of problematic interests, and venture exit provisions in the event sanctions come into force. U.S. sanctions sometimes provide for a wind-down period during which potentially affected entities can divest themselves of sanctioned interests. However, as we have seen under the Caesar Act, entities engaged in sanctioned conduct on or after the date the legislation was enacted are subject to sanction without any opportunity for their business partners to wind down their partnership with the entity. Getting legal advice ahead of any business dealings that may be impacted by sanctions is therefore critical.

Curtis has a world-class sanctions team who regularly advises governments and companies on sanctions-related issues around the world. We would be delighted to advise on any specific sanctions queries our clients may have.

[1] https://omanlawblog.curtis.com/2018/09/united-states-issues-executive-order.html

Read More...



Tuesday, February 11, 2020

Foreign Investment in Oman

Investment in Oman has now become more attractive to foreign individuals as a result of the new Foreign Capital Investment Law (Royal Decree 50/2019) (the “New FCIL”) that was published in the Official Gazette in the second half of 2019 and came into force on 1 January 2020.

Under the New FCIL, foreign investors can now set up investment companies in Oman without any capital requirements, and local participation is no longer mandatory. The Ministry of Commerce and Industry (the “MOCI”) further facilitates the registration of companies subject to the New FCIL by introducing an incentive package to ensure capital stability, allowing the transfer of profits abroad, and simplifying the licensing procedures.

The New FCIL contributes to attracting foreign investments, enhancing the Sultanate’s position as an investment destination capable of attracting foreign capital, and raising the Sultanate’s ranking in global indicators relating to ease of business and economic diversification, as well as reducing the silent partner arrangement that was common under the former FCIL.

The New FCIL will play an important role in attracting foreign investments and the flow of capital within the Sultanate by creating appropriate conditions for investment so as to be competitive in attracting investments from countries around the world, and granting incentives, privileges, and guarantees that contribute to the establishment of foreign investments.

The MOCI supports applications for the registration of foreign investment companies and seeks to facilitate and simplify procedures for obtaining all approvals, permits and licenses for investment projects; and an integrated team has been assigned to oversee these applications.

In addition, the New FCIL has included a number of incentives to encourage foreign investment, of which the most prominent are the following:

  • Allowing foreign investors to own 100% (as mentioned above);
  • The absence of a maximum foreign capital contribution; and
  • Omani investors can enter into a partnership with foreign investors without a specified minimum percentage.

Investment projects established by foreign investors, either alone or with the participation of others in the Sultanate, enjoy all the advantages, incentives and guarantees that national projects enjoy under the laws in force in the Sultanate. The incentive package includes the possibility of allocating government land and real estate necessary for the investment project by way of long-term lease or by granting a usufruct.

In order to establish foreign investments in the Sultanate, the New FCIL guarantees the rights of existing investment projects in the Sultanate, including that investment projects may not be confiscated, seized, frozen, or guarded, except by a court ruling; and debt is exempted from taxable income. Ownership of the project may only be expropriated for the public benefit and in return for fair compensation paid without delay. Likewise, usufruct or lease contracts may not be terminated where land or real estate has been allocated except in accordance with legally established precedents or by a court ruling; and the competent authorities may not withdraw the approval or license or permit issued for the investment project, unless the investor has committed a serious breach of the terms of his investment followed by a reasoned decision in writing after (i) warning the investor of the breach and (ii) giving 30 days from the date of warning to remedy the breach. If the breach has not been remedied, the MOCI will gradually impose administrative penalties on those in breach.

Read More...



Monday, January 13, 2020

WIthout Prejudice in Oman

The Omani courts do not recognise the concept of ‘without prejudice’ communications.  Any correspondence marked ‘without prejudice’ and brought into existence expressly for the purpose of furthering genuine settlement negotiations can be filed in court and relied on.  There are, however, several alternative steps that can be used in Oman to bolster the protection of any settlement correspondence.  By way of example, in any settlement negotiations, insist that all parties to the dispute sign an undertaking that any information disclosed in the communications will not be used as evidence before the courts.  Further, all documents should contain a statement or qualification that any offer does not constitute an admission of liability.  In addition, any settlement agreement should have a comprehensive confidentiality provision to prevent any form of publication.  A settlement agreement should also contain a provision preventing the parties from being called as witnesses in any subsequent litigation or arbitration in relation to the dispute.  A waiver of this condition should require consent of all parties.  Finally, if necessary, all communications in relation to a settlement should be made orally and not in writing.

Read More...



Monday, January 6, 2020

Dispute Resolution Clauses in Oman

A party must ensure that any final judgment granted in its favour is readily enforceable in all relevant foreign jurisdictions.  This is especially true where the opposing side is a foreign entity with assets vested offshore.  The 1996 Treaty for the Enforcement of Judgments, Judicial Delegation, and Courts Summons has made all Omani court judgments readily enforceable throughout the Gulf Cooperation Council (“GCC”).  If the opposing side has considerable assets in a neighbouring GCC country, a final binding Omani court judgment will be valuable, as it will be honoured and readily enforceable.  However, recognition and enforceability of an Omani court judgment in other foreign jurisdictions may vary, or perhaps be unclear.  All dispute resolution clauses should specify (i) the venue (i.e., the courts of a selected country or the seat of arbitration) and (ii) the substantive law which governs the underlying contract.  In instances where the parties grant jurisdiction to the domestic courts of a specific country, issues of venue and applicable law are invariably interlinked.

Read More...