Subcontracting is common in the modern construction industry. It would almost certainly be unmanageable for one contractor to deliver a construction project, especially if the project involves a certain level of complexity, without contracting third parties having various expertise and capabilities to carry out specific portions of the works. On the other hand, from the project owner’s perspective, it does seem more desirable to engage one main contractor who remains responsible for all the subcontractors. That being said, it is not surprising that the main players in most construction projects are the project owner (client/employer), the main contractor and subcontractor(s). This interactive chain naturally gives rise to a number of contractual and legal issues.
There are no provisions in Omani law prohibiting the main contractor from subcontracting the whole or part of the works to a third party without the need to obtain a permission from the employer, unless otherwise stipulated in the contract, or if the performance of the works depends on the personal competence of the contractor.
However, in practice, employers tend to have an element of control over the main contractor in subcontracting the works and the selection of subcontractors. The degree of such control varies. The contract may restrict the scope of subcontracting by way of prohibiting subcontracting the whole of the works. This provision is quite common in standard forms of contract: for example, Clause 4.4 of the FIDIC Red Book 1999 states that “[t]he Contractor shall not subcontract the whole of the Works.” The contract may further require the main contractor to obtain the prior consent of the employer or the engineer to engage a proposed subcontractor if that subcontractor is not nominated by the employer. In this respect, it may be advisable in some instances to ensure that the contract contains a provision that “… [s]uch consent shall not be unreasonably delayed or withheld….”
The subcontractor may be nominated by the employer (nominated subcontractor) or selected by the main contractor (domestic subcontractor). In both cases, the subcontract agreement is to be concluded between the main contractor and the subcontractor. Hence, there is no direct contractual relationship between the employer and the subcontractor. As a result: i) the subcontractor is not contractually liable towards the employer for delayed delivery or defective works; and ii) the employer is not contractually liable towards the subcontractor for the payment of its entitlements under the subcontract agreement. These two issues will be dealt with in turn.
Subcontractor’s liability to the employer
Privity of contract is a well-established doctrine under Omani law. The subcontractor, not being a party to a contract with the employer, it is not under any contractual obligation towards the employer or the subsequent owners under normal circumstances. The construction agreement between the employer and the main contractor may not impose an obligation on the subcontractor unless such obligation is accepted by the latter.
Accordingly, the main contractor remains liable to the employer for the subcontractor’s performance. Even in the case of a nominated subcontractor, the general rule is that the main contractor’s liability remains in place.
To minimise its scope of liability, the main contractor – especially if the contract does not provide for a right to object to nomination – may require the inclusion of an indemnity clause in the main contract whereby the employer indemnifies the main contractor against any damages that may occur as a consequence of the nomination.
Employer’s liability to the subcontractor
As illustrated above, there is no direct contractual relationship between the employer and the subcontractor. Consequently, the employer is under no obligation whatsoever to the subcontractor.
The subcontractor therefore has no option but to seek the payment of its dues from the main contractor. Practical problems occur when the subcontract agreement contains a “pay-when-paid” clause, which is commonly imposed by main contractors. Pay-when-paid clauses are enforceable under Omani law. The effect of a pay-when-paid clause is that the subcontractor is not able to claim its dues from the main contractor until the latter has been paid by the employer. If the subcontractor brings legal proceedings against the main contractor before the latter has been paid, the court may dismiss the case on the ground of premature filing of the claim.
To reduce the harshness of “pay-when-paid” clauses, the subcontractor may attempt to obtain a direct payment obligation from the employer when negotiating the contract. However, in practice, this is rarely acceptable to employers.
In some cases the subcontractor may argue that the non-payment by the employer is solely attributable to the main contractor’s fault – for example, if the main contractor fails to provide the performance bond as required under the main contract. In other circumstances, the subcontractor may argue that the main contractor is in breach because of its failure to pursue its claim against the employer. In this connection, it may be advisable that the subcontractor tries to agree a contractual clause whereby the main contractor will be under an obligation to pursue its claims against the employer to the greatest possible extent.
Conclusions
Subcontracting is permissible under Omani law and is prevalent in practice. Standard forms commonly provide for mechanisms restricting the scope of subcontracting. Under Omani law, subcontracting does not create a direct relationship between the employer and the subcontractor. Thus, the main contractor generally remains liable for the timely completion and quality of the subcontracted works. The main contractor may have grounds to defend itself against the liability for nominated subcontractors in particular circumstances. The subcontractor may not claim payments from the employer unless a direct payment obligation exists. Pay-when-paid clauses are commonly used in Oman. However, there are means to limit the effect of such clauses in particular cases.